Market data Poland battery storage, 1 Oct1.3 GW / 3 GWh1 Oct Li carbonate (GFEX)104,740 CNY/t▼ 11.8% d/d12 Oct Grid-scale BESS installed, Sep20.4 GWh▲ 61% y/y15 Oct Germany storage added, Jan–Sep8.2 GWh▲ 91% y/y30 Sep China new-type storage fleet, end-Sep167 GW / 435 GWh▲ 63% y/y30 Sep Bulgaria battery fleet, late Oct6.23 GW27 Oct Lithium132,771 $/t▼ 8.3% m/mOct 2026 avg Nickel15,436 $/t▼ 5.3% m/mOct 2026 avg Cobalt36,288 $/t▼ 13.7% m/mOct 2026 avg Manganese2,799 $/t▲ 0.6% m/mOct 2026 avg Latest published figures · click for source
Press release

ADS-TEC Energy wins repeat 10 MWh battery order from German utility SWLB

German storage maker ADS-TEC Energy will supply two more BESS5000 systems with a combined 10 MWh to Stadtwerke Ludwigsburg-Kornwestheim, a year after the utility's first 5 MWh order; commissioning is planned for summer 2027.

ADS-TEC Energy · · 1 min read

ADS-TEC Energy, the storage and fast-charging company based in Nürtingen, has received a repeat order from Stadtwerke Ludwigsburg-Kornwestheim (SWLB), a municipal utility in Baden-Württemberg. The release was published on 19 November with a Nürtingen/Ludwigsburg dateline.

The order

SWLB has ordered two further BESS5000 battery energy storage systems with a combined capacity of 10 MWh. They will be installed at the utility's Reuteallee site in Ludwigsburg, and commissioning is scheduled for summer 2027. The release gives no power rating and no contract value.

The order follows a first 5 MWh system that SWLB bought from ADS-TEC about a year ago. According to the company, that battery is now in operation at SWLB's wood-fired combined heat and power plant in Ludwigsburg.

Why the utility is adding storage

SWLB is building what it calls a decentralised storage strategy across its supply area. The batteries are meant to help integrate renewable generation, ease strain on the local grid and allow the utility to trade flexibility on energy markets. ADS-TEC says it develops its storage technology in Germany and integrates the main components into one system itself.

"We are pleased that SWLB has once again placed its trust in us," said Michael Rudloff, Chief Operating Officer of ADS-TEC Energy, adding that reliable individual systems are essential when building a decentralised storage network.

Sebastian Hess, responsible for strategy and corporate development at Stadtwerke Ludwigsburg, said SWLB also aims to support grid stability by taking part in the balancing market.

Context

The order is an example of a municipal utility combining local grid support with balancing-market revenues in a single small-scale battery fleet – the same revenue mix that underpins many of the storage projects now being built in Central and Eastern Europe, such as the Czech arbitrage and balancing batteries covered on CellsDesk this month.