Low Carbon brings 65 MW of solar-paired battery storage online in Essex
UK renewables company Low Carbon has put 65 MW of battery storage into commercial operation at two sites in Essex, its first co-located battery projects built in the UK. The 30 MW Birch battery shares a 132 kV grid connection with the 39 MW Birch and 49.9 MW Layer solar farms, while the 35 MW Sandon Brook battery sits next to a 49.9 MW solar farm of the same name that has also recently started operating.
No storage energy figure in MWh was published. Low Carbon says it has brought more than 200 MW of new renewable and storage capacity online in the UK since the start of 2026. Founder and chief executive Roy Bedlow called higher battery deployment "a key part of the solution helping to balance the grid".