Market data Poland battery storage, 1 Oct1.3 GW / 3 GWh1 Oct Li carbonate (GFEX)104,740 CNY/t▼ 11.8% d/d12 Oct Grid-scale BESS installed, Sep20.4 GWh▲ 61% y/y15 Oct Germany storage added, Jan–Sep8.2 GWh▲ 91% y/y30 Sep China new-type storage fleet, end-Sep167 GW / 435 GWh▲ 63% y/y30 Sep Bulgaria battery fleet, late Oct6.23 GW27 Oct Lithium132,771 $/t▼ 8.3% m/mOct 2026 avg Nickel15,436 $/t▼ 5.3% m/mOct 2026 avg Cobalt36,288 $/t▼ 13.7% m/mOct 2026 avg Manganese2,799 $/t▲ 0.6% m/mOct 2026 avg Latest published figures · click for source
BESS

Kyon Energy begins hot commissioning of 203 MWh Dahlem battery in Germany

CellsDesk Editorial ·

German developer Kyon Energy has started technical commissioning of its 100 MW / 203 MWh battery in Dahlem, North Rhine-Westphalia. In this "hot commissioning" phase the plant's electrical and control systems and its grid connection are tested under different operating conditions. Saft supplied 70 LFP battery containers, installed in October 2025, and the site's substation has two high-voltage grid connections that were energised in August.

When Kyon and Saft set the schedule in December 2025, they targeted energisation in the second quarter of 2026 and commercial operation in October. That date has been missed; Kyon now says operation should start shortly but gave no reason for the delay. Dahlem belongs to an 11-project portfolio in which Allianz Global Investors bought a 50% stake this year.

Written by CellsDesk in our own words from the source above; figures and company statements are as reported there. About CellsDesk